HB Ad Slot
HB Mobile Ad Slot
New Wheeling Charges for Renewable and Efficient Cogeneration Power Projects in Mexico
Thursday, June 11, 2020

On June 10, 2020, the Federal Electricity Commission (Comisión Federal de Electricidad, known as CFE), the Mexican utility operator, published in the Official Gazette (Diario Oficial de la Federación) the new wheeling fees for renewable and efficient cogeneration power projects that  executed an interconnection agreement with CFE prior to the energy reform in 2013.

The new wheeling charges are based on a resolution adopted by the CRE on May 28, 2020. It is worth mentioning that neither the resolution nor the methodology for the calculation of the new wheeling charges has been published in the Official Gazette by the Energy Regulatory Commission (CRE). This means that CFE is implementing resolutions adopted by the CRE that have not been enacted and are not in effect yet.

The new wheeling charges are the following:

Voltage  Wheeling Charges
June 2020 (peso/kWh 
New Wheeling Charges
(peso/kWh) 
Impact 
High Voltage  0.05100  0.27857  446% 
Medium Voltage  0.05100  0.25865  407% 
Low Voltage  0.10199  0.89284  774% 

Affected parties, meaning all companies that have a power generation permit granted by the CRE under the self-supply or power cogeneration scheme and have executed an Interconnection Agreement with CFE (a CIL) under the Public Electricity Service Law (Ley del Servicio Público de Energía Eléctrica), and the off-takers of such permits, are entitled to challenge these new wheeling charges through an amparo procedure.

Considering that the new wheeling charges may take effect in July 2020, the amparo claim should be submitted within 15 business days of June 10, 2020.

HB Ad Slot
HB Ad Slot
HB Mobile Ad Slot
HB Ad Slot
HB Mobile Ad Slot
 
NLR Logo
We collaborate with the world's leading lawyers to deliver news tailored for you. Sign Up to receive our free e-Newsbulletins

 

Sign Up for e-NewsBulletins