On 6 June 2013, the Italian Authority for Electricity and Gas (AEEG) announced that the overall annual expense cap of €6.7 billion for incentive payments payable to photovoltaic (PV) plants in Italy has been reached.
As a consequence, the latest feed-in tariff (FiT) regulation—the Conto Energia V—will cease to apply on 6 July 2013, i.e., 30 days from the AEEG’s announcement. PV plants that connected to the grid and started operations before 6 July will remain entitled to the currently applicable FiTs, as long as the relevant application is filed with the Gestore dei Servizi Energetici (GSE) before 6 July. Any application received after 6 July will be rejected.
The 6 July deadline also relates to PV plants installed on public land or public buildings that, pursuant to Section 1, Paragraph 425 of Legislative Decree no. 3584/2012 (the Stability Decree 2013), were entitled to an extension of the FiTs under the Conto Energia IV (see our Hot Topic of 3 January 2013).
Exceptions
Notwithstanding the Euro 6.7 billion cap being reached, certain PV projects are exempted from the 6 July deadline:
-
PV plants that are included in the first or second GSE’s register under Conto Energia V remain entitled to the Conto Energia V FiT and can apply to the GSE even after 6 July 2013, provided they start operations within one year of the publication of the register.
-
Special extensions also apply to PV plants that are located in certain Municipalities in the regions of Emilia Romagna and Lombardy, which were struck by earthquakes on 20 and 29 May 2012:
a) Roof top PV plants that started operating prior to the earthquakes remain entitled to the applicable FiT rate, even if they have to be rebuilt.
b) PV plants that were authorised on or before 30 September 2012, but hadn’t started operating before the earthquakes, remain entitled to the FiT provided by the Conto Energia IV for the first semester 2012, provided they start operations before 31 December 2013.
c) PV plants located on agricultural land are only entitled to the extension in b) above if the projects were authorised on or before 25 March 2012. They must still conform with the limits set forth under Article 10, Sections 4 and 5 of Legislative Decree no. 28/2011.
Finally, it is worth noting that the 6 July deadline does not apply to PV plants that applied for incentives or to be included in the registers but were rejected unlawfully. In these cases, where the applicant wins the appeal against the GSE, they will benefit from the FiT and the timelines provided under the Regulations as they were in force at the time of application.