On May 5, 2016, the IRS released new guidance regarding the renewable energy production tax credit (“PTC”) and energy investment tax credit (“ITC”) which most in the renewable energy industry will find favorable.
As enacted, the PTC and the ITC presently are subject to a sunset and will expire. Eligibility for either credit hinges on the date on which construction of the facility begins. As part of the Protecting Americans from Tax Hikes Act of 2015 (the “PATH Act”), Congress extended the PTC for two years, extending the date before which construction must begin for certain facilities to January 1, 2017, and extended the PTC for five years with respect to wind facilities by providing that construction must begin before January 1, 2020. Congress also modified the PTC for wind facilities by providing that the credit will phase out over the next four years. In addition, the ITC has been extended for solar energy facilities the construction of which begins before January 1, 2022.
In Notice 2016-31 (the “2016 Notice”), the IRS has updated its prior administrative guidance in order to implement the recent extensions of the PTC and the ITC. In response to a significant number of questions received after the extensions of these tax credits by the PATH Act, the 2016 Notice further extends and modifies the Continuity Safe Harbor (described below), and provides additional guidance regarding the application thereof as well as the Physical Work Test (also described below).
Tax Credit Eligibility
In general, a taxpayer producing electricity at a qualified facility may be eligible to receive the PTC, or, in lieu of the PTC (if the taxpayer so elects), the ITC. For purposes of these tax credits, examples of “qualified facilities” include wind facilities, closed-loop biomass facilities, open-loop biomass facilities, geothermal facilities, landfill gas facilities, trash facilities, hydropower facilities, and marine and hydrokinetic facilities.
When Does Construction “Begin”?
Prior administrative guidance was originally released on May 13, 2013 in IRS Notice 2013-29 (the “2013 Notice”). This guidance provides two methods by which a taxpayer may establish that construction of a qualified facility has begun: the “physical work” test and a “5% safe harbor.”
Physical Work Test
As set forth in the 2013 Notice, a taxpayer may establish the beginning of construction by starting physical work of a significant nature (the “Physical Work Test”). The “significant nature” determination focuses on the nature of the work performed, not the amount or cost (i.e., there is no fixed minimum amount of work or monetary or percentage threshold), and will depend on the relevant facts and circumstances (the 2013 Notice provides some guidelines and a nonexclusive list of examples in this regard, which have been supplemented by the 2016 Notice).
The IRS made explicit in the 2013 Notice that it will closely scrutinize a facility, and may determine that construction has not begun on a facility if the taxpayer does not maintain acontinuous program of construction (the “Continuous Construction Test”). The 2013 Notice explains that a “continuous program of construction” involves continuing physical work of a significant nature, and will be determined by the relevant facts and circumstances (certain disruptions in the taxpayer’s construction of a facility that are beyond the taxpayer’s control will not be considered as indicating that a taxpayer has failed to maintain a continuous program of construction).
5% Safe Harbor
Alternatively, a taxpayer may establish the beginning of construction by meeting the 5% safe harbor provided in the 2013 Notice (the “5% Safe Harbor”). To qualify for the 5% Safe Harbor, construction of a facility will be considered as having begun if:
- The taxpayer pays or incurs 5% or more of the total cost of the facility before the applicable deadline for satisfying the “beginning of construction” requirement (this 5% requirement is reduced to 3% in the case of a facility that is a single project comprised of multiple facilities, in which case special rules apply); and
- Thereafter, the taxpayer makes continuous efforts to advance towards completion of the facility (the “Continuous Efforts Test”).
For purposes of the first element of the 5% Safe Harbor, the “total cost of the facility” does not include the cost of land or any property not integral to the facility. For purposes of the second element, whether a taxpayer makes “continuous efforts to advance towards completion of the facility” will, again, be determined by the relevant facts and circumstances (the 2013 Notice provides a nonexclusive list of certain facts and circumstances that would indicate the requisite continuous efforts). Similar to above in the context of the Physical Work Test, certain disruptions in the taxpayer’s continuous efforts to advance towards completion of the facility that are beyond the taxpayer’s control will not be considered as indicating that a taxpayer has failed to make the requisite continuous efforts (the 2013 Notice provides a nonexclusive list of examples of such disruptions, and the 2016 Notice has supplemented that list).
Establishing Continuous Construction and Continuous Efforts
As described above, the two methods for establishing that construction of a facility has begun, for the purpose of qualifying for the PTC or ITC, require that a taxpayer make continuous progress towards completion once construction has begun, whether pursuant to the Continuous Construction Test or Continuous Efforts Test (as applicable). Following release of the 2013 Notice, the Treasury Department and IRS received a significant number of questions regarding the application of these tests. In response, the IRS issued Notice 2013-60 on October 28, 2013, which provided a method by which taxpayers may be deemed to satisfy both the Continuous Construction Test and the Continuous Efforts Test.
A facility will be considered to satisfy the Continuous Construction Test (for purposes of satisfying the Physical Work Test) or the Continuous Efforts Test (for purposes of satisfying the 5% Safe Harbor) if the facility is placed in service before January 1, 2017 (the “Continuity Safe Harbor”), regardless of the amount of physical work performed or the amount of costs paid or incurred with respect to the facility between December 31, 2014 and January 1, 2017.
The 2016 Notice extended the Continuity Safe Harbor from two years to four years from the end of the year in which construction began, such that if a taxpayer places a facility in service during a calendar year that is no more than four calendar years after the calendar year during which construction of the facility began, the facility will be considered to satisfy the Continuity Safe Harbor. The 2016 Notice provides the following helpful example: If construction begins on a facility on January 15, 2016, and the facility is placed in service by December 31, 2020, the facility will be considered to satisfy the Continuity Safe Harbor.
Observation: The failure to satisfy the Continuity Safe Harbor does not mean that a facility has not satisfied the requisite continuity. It means only that the determination will be based on the relevant facts and circumstances, as described above.
Prohibition Against Alternating Methods
Although a taxpayer may be able to satisfy both the Physical Work Test and the 5% Safe Harbor, it need only satisfy one method to establish that construction of a facility has begun for the purpose of qualifying for the PTC or ITC. However, the IRS stated in the 2016 Notice that a taxpayer may not rely upon the Physical Work Test and the 5% Safe Harbor in alternating calendar years to satisfy the beginning of construction requirement or the continuity requirement. The 2016 Notice provides the following example in this regard: If a taxpayer performs physical work of a significant nature on a facility in 2015, and then pays or incurs 5% or more of the total cost of the facility in 2016, the Continuity Safe Harbor will be applied beginning in 2015, not in 2016. The effect of this rule is to prevent a taxpayer from extending the four-year safe harbor period by relying on another method in a subsequent year. The taxpayer is essentially bound by whichever method is satisfied first.
Disaggregation
The 2016 Notice clarifies that multiple facilities that are part of a single project may be disaggregated for purposes of determining whether a specific facility satisfies the Continuity Safe Harbor or the continuity requirement under a facts and circumstances analysis (as applicable), such that each facility may be able to take advantage of the tax credit.
5% Safe Harbor & Retrofitted Facilities
Generally, under an “80/20 rule,” a facility may qualify as originally placed in service (and thereby qualify for the tax credit) even if it contains used property, as long as the fair market value of the used property is not more than 20% of the facility’s total value. Under the 2016 Notice, this “80/20 rule” is applied to each individual facility comprising a single project, and the 5% Safe Harbor is applied only with respect to the cost of new property used to retrofit an existing facility.
Takeaways
The 2016 Notice is good news for the renewable energy industry. The extension of the Continuity Safe Harbor from two to four years should benefit taxpayers developing larger projects, some of whom had commented that the two-year window was not feasible. This extension generally gives taxpayers more than four years to complete their renewable energy projects once physical work of a significant nature has commenced or once 5% or more of the total cost of the project has been incurred, since the four-year clock begins at the end of the year in which construction began.
Furthermore, the IRS’s addition of several new excusable disruptions that will not be taken into account in determining whether the Continuity Safe Harbor is satisfied will allow projects that experience certain delays (e.g., due to delays in obtaining permits or licenses, or due to severe weather conditions or natural disasters) to still qualify even if placed in service outside the four-year period.
Taxpayers should consider how the new guidance impacts their renewable energy development plans, and should consult with their tax advisors regarding whether they may qualify for the PTC or ITC in light of the new rules. The IRS will not issue private letter rulings to taxpayers regarding the application of the 2016 Notice or the application of the “beginning of construction” requirement. Renewable energy developers are encouraged to plan accordingly and begin construction on projects that are part of their four-year development pipeline if they intend to claim the tax credits.
Finally, taxpayers should continue to monitor additional guidance that may be issued by the IRS and the Treasury Department. IRS personnel have stated publicly that the rule preventing use of the Physical Work Test and the 5% Safe Harbor in alternating calendar years may be reconsidered. Additionally, the 2016 Notice indicates that the Treasury Department and the IRS anticipate issuing separate guidance addressing the extension of the ITC for solar energy facilities.